Cracking the Code: Estimate at Completion (EAC) of a Clinical Trial

Project management is a continuous loop of planning what to do, checking on progress, comparing progress to plan, taking corrective action if needed, and re-planning. The fundamental items to plan, monitor, and control are time, cost, and performance so that the project stays on schedule, does not exceed its budget, and meets its specifications.  Of course all of these activities are based on having an agreed upon Work Breakdown Structure (tasks/activities) on which to base the schedule and cost estimates.  During the planning phase of a project, the project manager with the assistance of the project team needs to define the process and procedures that will be used during the implementation phase to monitor and control the project’s performance.

Productivity in the pharmaceutical/biotech/medical device industry is going down. Some compounds have reached the billions expenditures cost without any guarantee that it will ever be approved or reach the market.  So how can we evaluate the performance of some of these clinical trials?

I will not go into details in the degree of project management activities managed and performed by a data manager since this can vary widely per company.  A good clinical data manager or manager of data management should be able to implement basic PM principles that will improve quality and timeliness of a clinical trial, regardless if the trial is fully outsourced (e.g. CRO performed most of the work).

You can find my article about the Role of Project Management in Clinical Data Management (2012) here for further reading.

So what is Estimate at Completion or EAC? or What is the project likely to cost?

There are several methods we could use to calculate EAC.

Let’s look at one formula. EAC =  AC (Actual Cost) + ETC (Estimate to Complete)  so what happens when you don’t know the ETC?

We could use the following formula to derive that value: ETC = (BAC – EV) / CPI =>>>>??? So what? More formulas? How do I get BAC or EV or CPI?

Let’s look at those in more details.

 BAC =>>>Budget at Completion (how much did you
budget for the total project?)
CPI =>>> Cost Performance Index (CPI): BCWP/ACWP

EV = Earned Value

Earned Value Analysis example for a phase 1 trial (*figures in the thousands / millions = fictitious  numbers)

The final clinical trial results includes 100 subjects. The estimated cost is $20 per subject.  That results in an estimated budget of $2000 (100 x 20). During the planning, the CRO indicated that would be able to enroll 5 subjects per week.  Therefore the estimated duration of the trial is 20 weeks (100 / 5)

EV blocks: From the project plan

Estimated Budget: $2000

Estimated Schedule: 20 weeks

Planned Value (PV): at the end of the trial is $2000

Variance between planned and actual at the end of the first week:

Based on the estimated scheduled, I should have 25 subjects enrolled. At $20 per subject, the planned value at the end of the week is $500 (25 x 20)

PV = $500

At the end of the first week, the CRO reports that he has enrolled 20 subjects  and the actual cost of that study is $450. With this information we can look at schedule and cost variance.

SV = EV – PV

SV = $400 – $500 = – 100 ($100 work of subject recruitment is behind schedule).

CV = EV – AC

CV = $400 – $450 = -50 ($50 work of the project is over budget)

*negative figures means bad.

Using early results to predict later results:

Schedule Performance Index (SPI)

SPI = EV/PV

SPI = 400/500 = .80

Cost Performance Index (CPI)

CPI = EV/AC

CPI = 400/450 = .89 –> over budget or expending more

These rations can be used to estimate performance of the project to completion based on the early actual experience.

Estimate to Completion (ETC)
ETC= (PV at completion) – EV)/CPI

ETC= (2000 – 400)/CPI

ETC = (1600/.89) =$ 1798 from end of week one (after 5 days) and it will take additional $1798 to complete the study

Estimate at Completion (EAC)

EAC = AC + ETC

EAC = 450 + 1798 = $2248

If nothing changes, based on the actual results at the end of the first week, the study is estimated  to cost $2248 (rather than the planned cost of $2000) and will take 20 percent longer.

The formulas assumes that the accumulative performance reflected in the CPI is likely to continue for the duration of the project.

You do not need to memorize all of these formulas. There are plenty of tools in the industry that does the computation for you. But if you do not have it available, you can use Excel, set-up your template and plug in the numbers.

Earned Value

 

 

 

 

 

 

 

As per PMI – PMBOK definition, Cost management “…includes the processes involved in estimating, budgeting, and controlling costs so that the project can be completed within the approved budget.”   A Guide to the Project Management Body of Knowledge (PMBOK® Guide).

We have shown you, that PM tools such as Earned Value  Analysis, can be applied to clinical trials or specific work break down (WBS) activities within the data management team.

Based on the above outcome of the project performance related to the schedule, the data manager should be able to determine if she should modify the current plan or revise the original plan.

It is a perfect tool for data managers and managers of data managers and could be part of your risk based processes.

If bringing efficiency, improving data quality and significantly reducing programming time after implementing CDISC standards is on your radar screen, I’d love to chat when it’s convenient. All the best.

Anayansi Van Der Berg has an extensive background in clinical data management as well as experience with different EDC systems including Oracle InForm, InForm Architect, Central Designer, CIS, Clintrial, Medidata Rave, Central Coding, OpenClinica Open Source and Oracle Clinical. SAS, CDASH/SDTM (CDISC standards implementation and mapping), SAS QC checks and clinical data reporting.

Source:

A Guide to the Project Management Body of Knowledge (PMBOK® Guide).

Notes from my PM class at Keller 2007-2009

Images – Google images

FAIR USE-
“Copyright Disclaimer Under Section 107 of the Copyright Act 1976, allowance is made for “fair use” for purposes such as criticism, comment, news reporting, teaching, scholarship, and research. Fair use is a use permitted by copyright statute that might otherwise be infringing. Non-profit, educational or personal use tips the balance in favor of fair use.”

Advertisements

PM Hats – Six Thinking Hats in Project Management

Six Thinking Hats

Looking at a Decision From All Points of View

‘Six Thinking Hats’ is an important and powerful technique. It is used to look at decisions from a number of important perspectives. This forces you to move outside your habitual thinking style, and helps you to get a more rounded view of a situation.

This tool was created by Edward de Bono’s book ‘6 Thinking Hats‘.

Many successful people think from a very rational, positive viewpoint. This is part of the reason that they are successful. Often, though, they may fail to look at a problem from an emotional, intuitive, creative or negative viewpoint. This can mean that they underestimate resistance to plans, fail to make creative leaps and do not make essential contingency plans.

Similarly, pessimists may be excessively defensive, and more emotional people may fail to look at decisions calmly and rationally.

If you look at a problem with the ‘Six Thinking Hats’ technique, then you will solve it using all approaches. Your decisions and plans will mix ambition, skill in execution, public sensitivity, creativity and good contingency planning.

How to Use the Tool

You can use Six Thinking Hats in meetings or on your own. In meetings it has the benefit of blocking the confrontations that happen when people with different thinking styles discuss the same problem.

Each ‘Thinking Hat’ is a different style of thinking. These are explained below:

  • White Hat: neutral and objective, concerned with facts and figures
    With this thinking hat you focus on the data available. Look at the information you have, and see what you can learn from it. Look for gaps in your knowledge, and either try to fill them or take account of them.This is where you analyze past trends, and try to extrapolate from historical data.
  • Red Hat: the emotional view
    ‘Wearing’ the red hat, you look at problems using intuition, gut reaction, and emotion. Also try to think how other people will react emotionally. Try to understand the responses of people who do not fully know your reasoning.
  • Black Hat: careful and cautious, the “devil’s advocate” hat * 
    Using black hat thinking, look at all the bad points of the decision. Look at it cautiously and defensively. Try to see why it might not work. This is important because it highlights the weak points in a plan. It allows you to eliminate them, alter them, or prepare contingency plans to counter them.Black Hat thinking helps to make your plans ‘tougher’ and more resilient. It can also help you to spot fatal flaws and risks before you embark on a course of action. Black Hat thinking is one of the real benefits of this technique, as many successful people get so used to thinking positively that often they cannot see problems in advance. This leaves them under-prepared for difficulties.
  • Yellow Hat: sunny and positive 
    The yellow hat helps you to think positively. It is the optimistic viewpoint that helps you to see all the benefits of the decision and the value in it. Yellow Hat thinking helps you to keep going when everything looks gloomy and difficult.
  • Green Hat: associated with fertile growth, creativity, and new ideas
    The Green Hat stands for creativity. This is where you can develop creative solutions to a problem. It is a freewheeling way of thinking, in which there is little criticism of ideas. A whole range of creativity tools can help you here.
  • Blue Hat: cool, the color of the sky, above everything else-the organizing hat 
    The Blue Hat stands for process control. This is the hat worn by people chairing meetings. When running into difficulties because ideas are running dry, they may direct activity into Green Hat thinking. When contingency plans are needed, they will ask for Black Hat thinking, etc.

Exercise:

Here’s an exercise (inspired by Bono ideas) which will work very well with those who have been required to read Six Thinking Hats prior to getting together to brainstorm. Buy several of those delightful Dr. Seuss hats (at least one of each of the six different colors, more if needed) and keep the hats out of sight until everyone is seated. Review the agenda. Review what de Bono says about what each color represents. Then distribute the Dr. Seuss hats, making certain that someone is wearing a hat of each color. Proceed with the discussion, chaired by a person wearing a Blue or White hat. It is imperative that whoever wears a Black hat, for example, be consistently negative and argumentative whereas whoever wears a Yellow must be consistently positive and supportive. After about 15-20 minutes, have each person change to a different colored hat. Resume discussion.

Six Thinking Hats” is about improving communication and decision-making in groups.

Summary: Bono puts thinking into steps: 1. Information 2. Benefits 3.Critical thinking 4. Feelings 5. Creative thinking 6. Thinking about the thinking and creating and action plan for implementation.

How would you incorporate the ‘Six Thinking Hats’ in clinical data management?

Reference:

Six Thinking Hats by Edward de Bono, 1999

http://www.mindtools.com

Fair Use Notice: This blog/article/video contains some copyrighted material whose use has not been authorized by the copyright owners. We believe that this not-for-profit, educational, and/or criticism or commentary use on the Web constitutes a fair use of the copyrighted material (as provided for in section 107 of the US Copyright Law).

If you wish to use this copyrighted material for purposes that go beyond fair use, you must obtain permission from the copyright owner. Fair Use notwithstanding we will immediately comply with any copyright owner who wants their material removed or modified, wants us to link to their website or wants us to add their photo.

Disclaimer: The EDC Developer blog is “one man’s opinion”. Anything that is said on the report is either opinion, criticism, information or commentary. If making any type of investment or legal decision it would be wise to contact or consult a professional before making that decision.

Disclaimer:De inhoud van deze columns weerspiegelen niet per definitie de mening van {EDC Developer}.

Professional Timeline – Clinical Programmer

Professional Timeline

Curriculum Vitae
CV

 

anayansi gamboa